40 hours a week back for a commercial and projects team of 10
A housebuilder trained its commercial and projects team on Copilot over 8 weeks. Between them they got back a full working week, every week, and ran a fifth site without the extra QS they’d been about to hire.
Key results
- 45 → 15 minsChecking a subcontractor application
- 8 → 3 hoursCost to complete, each site, each month
- 64 → 24 hoursAll 7 jobs, the whole team, each week
- The business
- Housebuilder
- Service
- Copilot Training
- Trained in
- 8 weeks
- Paid back in
- Approx 8 weeks
- Size
- Team of 10 trained
Background
The business was growing. 4 live sites, a fifth starting in the spring, and the same commercial and projects team of 10 that had run 3. They had a good team, and the commercial director wanted to keep it.
The challenge
Each month more of their week went on paperwork. The QSs checked about 30 subcontractor applications a week against the plot-stage report, and the cost to complete took about a day a month on each site. The full check against the appraisal waited for the quarterly forecast.
Before advertising for another QS, the MD asked each person to log a normal week. Across the 10 of them, 7 jobs took 64 hours a week.
They had the free Copilot Chat, and moved to Microsoft 365 Copilot licences for the training. The QSs wanted proof on numbers, and a clear rule on what could go in.
2,900 hoursa year on 7 jobs Copilot could help with
The solution
The training ran for 8 weeks on their own live work. Every session used that week’s applications and cost reports, so nothing got left behind. The directors went first, so the teams saw them using it, and each team had a champion to keep it going.
What the 8 weeks covered
- Directors first. A session on their own in week 1. Then all 10 timed their jobs and signed a one-page AI policy.
- Commercial. Hands-on sessions on applications, then applications against the plot-stage report, then the cost to complete against the appraisal.
- Projects. Site reports, programme updates, customer extras and site instructions.
- The 3 checks. Every fact has its source next to it, every number gets worked out again in the spreadsheet, and whoever’s name is on it reads the lot.
Tech stack
It runs on their own Microsoft 365. It works alongside the tools they already use.
The results
- 01
A fifth site, with no extra QS
When the fifth site started in the spring, the same team of 10 ran it, with no new hire, on a bigger turnover.
- 02
£24,000 held on one site’s brickwork
The first monthly appraisal check, in week 6, found brickwork tracking £1,600 a plot over the appraisal, with 24 plots to go. A detail change and a fixed rate with the bricklayer held £1,000 a plot.
- 03
10 of 10 using it every week
In week 1, 2 of them had tried it. Average confidence went from 3.4 out of 10 to 7.6.
- 04
The appraisal checked every month, not every quarter
It used to wait for the quarterly forecast.
More case studies
See all case studies
Main contractorPackaging a tender went from 19 hours to 5Read the case study
M&E contractorReading an M&E spec went from 6 hours to 2.5Read the case study
Main contractorDeciding whether to price a tender went from 6 days to 1Read the case study
Main contractorThe final tender check went from a day to 30 minutesRead the case study
Main contractorPricing a variation went from 14 days to 3Read the case study