Feasibility Study for Brackwell Tarn Construction

01 / 11

Feasibility Study

Brackwell Tarn Construction

Where your team’s time goes on valuations, tenders and site reports, what it takes to get it back, and when the cost is covered.

EXAMPLE

What this study finds (modelled)

VALUATIONS AND PAYMENTS

About 1,690 hours a year

back to your commercial team

TENDERS AND ESTIMATING

About 985 hours a year

back to your estimating team

SITE REPORTS AND RECORDS

About 565 hours a year

back to your site team

TRAINING

60 people trained

to use approved tools on everyday work, safely

Prepared forThe Managing Director, Brackwell Tarn Construction
ScopeValuations and payments, tenders and estimating, site reports and records, and training. 60 of your 60 people.
Version1.0, 30 September 2026
Delivered withAn editable workbook with the full model, process records, build briefs and acceptance checks

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

02 / 11

The decision

Start with valuations and payments.It covers its monthly fee from month 3and pays for itself in month 7 (modelled).

Fix valuations and payments first, then tenders and estimating, then site reports and records, with training alongside. The recommended route is the AI Partnership: £10,750 + VAT a month, six-month minimum.

Year-one value

£222,559

modelled staff time value

Year-one cost

£110,690

fees £64,500, software £14,400, your staff time £31,790

Pays for itself

Month 7

when modelled value passes the total cost. Covers the monthly fee from month 3.

Recommended route

AI Partnership: £10,750 + VAT a month, six-month minimum (£64,500)

All three builds and all training in one plan. Something built or improved every month, and your team trained on it. The other two routes are on page 9.

When this holds

If effective use reaches about 39.8%, against the 80% assumed, with all areas falling together and costs fixed. Below that, year one does not cover its cost.

Staff time, not cash

Every value here is staff time at employment cost. Decide now where freed hours go: more work delivered, less overtime, or fewer subcontracted hours.

Stays with your people

Measurement and valuation. Prices, terms and client promises. Every sign-off before anything is issued or submitted.

Nothing has been built, tested or measured during this study. Every benefit is a forecast until it is re-measured after each build.

Next step: name your sponsor and record owners this week. See page 11 →

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

03 / 11

Your business now

4 places to win back time.Keep your core systems.

60 people across Head office in Leeds, with live sites across Yorkshire, 60 of them in scope. Microsoft 365, SharePoint, Excel, your accounts system and your estimating software stay as they are. AI use today is occasional, with no agreed rules.

Ranked by how fast and how surely each pays for itself

1

Valuations and payments

Largest recurring workload. 14 live projects a month, 110 team hours a week.

£79,376

year one, modelled

38.4 of 110 hours a week back

2

Tenders and estimating

Reuses the same approved tender library. 3 enquiries a week.

£41,785

year one, modelled

22.4 of 90 hours a week back

3

Site reports and records

Next on the list, built inside the AI Partnership. 14 weekly reports, 60 team hours a week.

£18,715

year one, modelled

12.8 of 60 hours a week back

4

Training

Widest reach, weakest evidence. 60 people, 6 cohorts.

£82,683

year one, modelled

10 minutes a day each for 48 active people (assumption)

The process fixes carry most of the modelled value and are the best evidenced. Your AI Self-Assessment gave a range for each. This study narrows each to one figure from your own records.

Sort first, before any build

Name the owner of each record. Record the current templates. Confirm no client material leaves your Microsoft 365 tenant.

Not in this study

Contract disputes, final accounts and subcontractor payments, which are separate decisions. Site safety systems and an IT audit.

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

04 / 11

Valuations and payments

Get about 38 hours a week backfrom valuation work (modelled).

Today 8 people spend 110 hours a week on 14 live projects valued each month. That is about £266,200 a year of staff time (110 hours × 44 weeks × £55).

Today

  • Live projects valued each month

    14

  • Team hours a week

    110

  • People

    5 quantity surveyors, 2 site managers, 1 commercial manager

  • Already works well

    Applications go in on the contract date, with commercial sign-off

What changes

A valuation assistant inside your Microsoft 365

  • Site records, instructions and the valuation workbook go in
  • A draft application comes out in your format, every line linked to its record
  • Missing evidence is listed before your commercial manager sees it
  • Nothing is submitted until your commercial manager signs it off

Today’s six steps, and where they break

Site manager

Record the progress

Quantity surveyor

Measure and value

Version hunting

Quantity surveyor

Price the variations

Repeated collation

Quantity surveyor

Compile the application

Repeated collation

Commercial manager

Check and approve

Gaps found late

Commercial coordinator

Submit and follow up

Hours a week, before and after

StageTodayAfter (80% use, from month 4)
Record progress, measure and value45 h45 h
Price variations, compile and submit65 h26.6 h
Total110 h71.6 h

38.4 hours

back each week

1,690 hours

back each year

£92,928

a year of staff time value at steady use

Not claimed: faster payment or fewer disputed items, because there is no baseline yet. No cash-flow benefit is counted.

Stays with your people

Measurement, the value of each variation, the amount applied for and permission to submit.

The build

£6,000 + VAT, fixed. One application format per contract type, up to 20 projects a month, 7 users.

Not included: final accounts, dispute papers, subcontractor payments, anything sent to a client without sign-off.

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

05 / 11

Tenders and estimating

Get about 22 hours a week backfrom tender writing (modelled).

Today 5 people spend 90 hours a week on 3 tender enquiries a week. That is about £217,800 a year of staff time (90 hours × 44 weeks × £55).

Today

  • Tender enquiries a week

    3

  • Team hours a week

    90

  • People

    1 estimating manager, 3 estimators, 1 coordinator

  • Already works well

    A clear bid or no-bid decision, and every tender logged

What changes

A tender assistant working from your approved library

  • The tender documents go in
  • Every requirement and missing item is listed
  • A draft is made from your approved tender library only
  • Your director approves price and terms, and your estimating manager submits

Today’s six steps, and where they break

Estimating coordinator

Log the enquiry

Incomplete records

Estimating manager

Decide to bid

Estimator

Read the tender documents

Repeated chasing

Estimator

Get trade prices

Estimator

Build the tender pack

Repeated drafting

Director

Review and submit

Approval queue

Hours a week, before and after

StageTodayAfter (80% use, from month 5)
Log, decide and read35 h35 h
Price, compile and submit55 h32.6 h
Total90 h67.6 h

22.4 hours

back each week

986 hours

back each year

£54,208

a year of staff time value at steady use

Not claimed: any change in your win rate, because there is no baseline yet.

Stays with your people

Price, margin, programme commitments, exclusions, terms and the final submission.

The build

£6,000 + VAT, fixed. Two tender formats, up to 16 tenders a month, 5 users.

Not included: pricing itself, a new estimating system, data migration, portal automation.

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

06 / 11

Site reports and records

Get about 12 hours a week backfrom weekly reporting (modelled).

Today 12 people spend 60 hours a week on 14 live projects reported each week. That is about £145,200 a year of staff time (60 hours × 44 weeks × £55).

Today

  • Live projects reported each week

    14

  • Team hours a week

    60

  • People

    10 site managers, 1 contracts manager, 1 project coordinator

  • Already works well

    Diaries are kept every day and reports go out every week

What changes

A site report assistant inside your Microsoft 365

  • The week’s diary entries and photos go in
  • A draft report comes out in the client’s format, photos placed
  • Your site manager corrects it and your contracts manager approves it
  • Nothing goes to a client until it is approved

Today’s six steps, and where they break

Site manager

Keep the daily diary

Site manager

File the photos

Repeated filing

Site manager

Write the weekly report

Repeated drafting

Contracts manager

Check and approve

Approval queue

Project coordinator

Send and file

Contracts manager

Answer client queries

Version hunting

Hours a week, before and after

StageTodayAfter (80% use, from month 7)
Keep the diary and file the photos25 h25 h
Write, check and send the weekly reports35 h22.2 h
Total60 h47.2 h

12.8 hours

back each week

563 hours

back each year

£30,976

a year of staff time value at steady use

Not claimed: faster answers to client queries or claims, because there is no baseline yet.

Stays with your people

What is said about progress, delays and risks, anything sensitive, and permission to send.

The build

Built inside the AI Partnership fee, live in month 5. Three client report formats, up to 20 projects a week, 11 users.

Not included: health and safety reports, incident records, programme updates, anything sent to a client without approval.

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

07 / 11

Training

Train 60 people to use approvedtools on everyday work, safely.

One practical day for each cohort of up to 10, built on your own documents. 6 cohorts across months 1 to 3.

Who

  • Office, coordination and site management

    Clear correspondence, accurate actions, dependable checking.

  • Commercial and estimating staff

    Routine analysis from sources, within their own authority.

What they practise

  • Emails and letters

    Draft, check and adapt to the job.

  • Site meeting notes

    Turn approved notes into clear actions.

  • Spreadsheets

    Check figures and explain the differences.

The assumption beside the break-even (minutes a day, per active person)

Modelled gain (assumption)

10 min

Break-even at steady use

6.5 min

Break-even in year one, while the ramp builds

7.6 min

The margin between the gain and the break-even is 2.4 to 3.5 minutes a day. That is thin, and it is the least proven part of this study.

Year one

£82,683 modelled value against £62,870 cost

1.32 times.

What the £62,870 is

Training fee£18,000
Your people’s attendance£24,750
Software licences£14,400
Practice, set-up and support£5,720
Total£62,870

The £14,400 licences are the same single set shown in the total on page 8, not a second bill. Valuation, tender and weekly report work is left out of the training line, so no hour is counted twice. Modelled for 48 active people: 80% of the 60 trained.

What it needs from you

An internal sponsor. Protected time to attend. Your own material to practise on. A named person to follow through after each day.

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

08 / 11

The numbers

It pays for itself in month 7,if use holds (modelled).

Year one: £222,559 modelled value against £110,690 cost, 2.01 times. Supplier fees £64,500. Software licences £14,400, paid to software suppliers, not Built Logic. Your staff time £31,790.

£150k£100k£50k£0k−£50k Start3 months6 months9 months12 months Lowest: −£21,775 in month 3Pays for itself in month 7+£111,869

Modelled staff time value less cost, added up month by month. Not cash flow. Supplier fees £10,750 a month in months 1 to 6. Licences and staff time £3,849 a month across months 1 to 12. Each month’s modelled value passes the £10,750 fee from month 3.

The three ways compared, year one (shared costs counted once)

RouteValueCostBalance
Custom-Built Systems, both processes
Fees £11,000, licences for 12 users £2,880, acceptance time £880
£121,161£14,760£106,401
Training only£82,683£62,870£19,813
AI Partnership: all three builds, plus training and support£222,559£110,690£111,869

The process fixes stand on their own. Training adds more value, on a thinner and less proven margin.

The inputs (all illustrative in this example)

Staff time cost£55 an hour (employment cost, not salary)
Working weeks44 a year
Effective use80% of eligible hours, with 48 of 60 trained people active
Training gain10 minutes a working day, 220 days
RampValuations and payments from month 2, full use by month 4. Tenders and estimating from month 3, full use by month 5. Site reports and records from month 5, full use by month 7. Training from month 2, full use by month 4
Licences£20 a person a month, 60 people, counted once
Your staff time578 hours: training 554, build acceptance 24

If use is lower

Break-even at about 39.8% effective use, with all areas falling together and costs fixed. At 40%, half the modelled use, year one is £111,280 against £110,690: still £590 ahead.

Year two (assumption)

Supplier fees stop. Running cost about £46,190 a year (licences and your staff time, assuming participation continues at year-one level) against about £274,900 steady-year modelled value.

Not claimed: rework reduction, win rate, cash savings, fee income.

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

09 / 11

Three ways to go ahead

Choose how much help you want.Each route works on its own.

Software, hosting and your staff time are separate on every route. All prices exclude VAT.

Training

£18,000

one-off

  • 6 tailored days, one per cohort of up to 10
  • 60 people trained on your own material

No builds and no ongoing support. One-Day Training, not tailored to your work, is £2,500 for up to 10.

Custom-Built Systems

£11,000

for both builds

  • Valuation assistant £6,000 and tender pack assistant £6,000, less £1,000 for one shared handover day
  • Handover training, the first month of support after go-live, and a follow-up a month after go-live

No training (add it for £18,000: £29,000 together) and no ongoing improvement. After the first month, support is a monthly Support Plan, agreed with the build.

AI Partnership

Recommended

£10,750

a month, six-month minimum (£64,500)

  • All three builds and all 6 training days
  • One process fixed or improved every month, and your team trained to run it
  • A monthly review of what is in use and what it put back
  • A six-month check against what was agreed at the start

Why the AI Partnership costs £35,500 more

Builds and training bought separately come to £29,000. The AI Partnership is £64,500 over its six-month minimum. The £35,500 difference pays for the site report assistant, built inside the fee, and the monthly fixes and reviews after the tools go live, so they keep improving instead of standing still.

Your study fee

Your £2,000 study fee is credited against your first AI Partnership invoice if you start the AI Partnership within 30 days of this study. It does not apply to training or a one-off build.

Payment terms for the delivery you choose are agreed in writing with its scope.

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

10 / 11

The plan

Something built or improved everymonth, and your team trained on it.

Six months on the recommended route. Each tool goes live only after your people accept it.

MonthBuilt or improvedTrainedYour side
1Record control and templates agreed; valuation assistant built and tested on 10 real applicationsRecord owners on the templates and access rules, plus cohorts 1 and 2Commercial manager supplies templates and 10 test cases
2Valuation assistant live after acceptance; tender pack assistant built and tested on real tendersCommercial team at handover, plus cohorts 3 and 4Commercial manager accepts; estimating manager supplies the library and test cases
3Tender pack assistant live after acceptanceEstimating team at handover, plus cohorts 5 and 6Estimating manager and director accept
4Site report assistant built and tested on 10 real weekly reports; valuation assistant improved from its first roundsSurveyors on the changesContracts manager supplies report formats and 10 test cases
5Site report assistant live after acceptance; tender pack assistant improved from its first tendersSite managers at handover, plus estimators on the changesContracts manager accepts; estimating manager lists what to change
6All three improved from use so farA refresher for the people leading each toolSix-month check against what was agreed. Decide who runs all three from month 7

What “accepted” means

  • Every line is traceable to a record
  • Missing evidence is raised before review
  • Client material stays in your Microsoft 365 tenant
  • No valuation judgement is generated
  • A manual fallback that works
  • Only authorised material can be reached
  • Every answer is traceable to a source
  • Nothing is submitted without a named approver

How you will know

Each build is re-measured at week 8 and week 12 after it goes live, the same way as this study.

So you compare like with like. Full evidence and owners for each check are in the workbook.

Example. Company and figures are illustrative.
Read with: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

Commercial in confidence

BUILT LOGIC

Feasibility Study for Brackwell Tarn Construction

11 / 11

Your plan to keep

This plan is yours.Use it with Built Logic or without.

Everything another provider needs to quote against the same scope is in the workbook. Compare any provider on the same scope and checks, not the headline fee.

The workbook: Brackwell Tarn Construction Feasibility Study workbook v1.0.xlsx

1  Inputs

Every input, its label and its source

2  Monthly model

Value and cost by month, 24 months

3  Routes

Each route’s value and cost, shared costs once

4  Process records

Each process, stage by stage

5  Build briefs

Users, volumes, inputs, outputs, exclusions

6  Acceptance

Every check, its evidence and its owner

7  Sources and open items

Each with an owner, a deadline and its effect

What the figures rest on

Your valuation and tender records, your finance team’s employment cost and owner estimates by stage, and the inputs on page 8. Nothing has been built, tested or measured during this study. Every benefit is a forecast until it is re-measured after each build.

Still open

ItemOwnerByEffect
Rate of disputed or reduced valuation itemsCommercial managerMonth 2No benefit claimed until it is measured
Exact role counts in each processOperations sponsorMonth 1Confirms hours and users for each build
Current template versionsRecord ownersMonth 1Needed before either build starts
Each client’s report formatContracts managerMonth 3Needed before the site report build starts
Permissions and access rulesSystem ownerMonth 1Needed before any client material is used

Your next step

Name your sponsor and record owners this week.